Central B - Sonoma Highway 101 HOV Lane Widening |
Description: On US 101, from south of Old Redwood Highway Overcrossing to north of Pepper Road. Widen freeway from four to six lanes.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sonoma |
City | |
Zip Code | |
Senate District |
03 |
Assembly District | 06 |
Congressional District | 06 |
Caltrans District |
04 |
County/State Route | Sonoma 101 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 965 | |
Lane Miles Added (HOV) | 1.8 | |
Lane Miles Added (Mixed) | 0 | |
Peak Period Time Savings (minutes) | 965.0 | 70432 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Sonoma County Transportation Agency | Betcy Joseph | (510) 286-5097 | betcy.joseph@dot.ca.gov | |
Design (PS&E) Phase |
Sonoma County Transportation Agency | Betcy Joseph | (510) 286-5097 | betcy.joseph@dot.ca.gov | |
Right of Way Phase |
CalTrans | Betcy Joseph | (510) 286-5097 | betcy.joseph@dot.ca.gov | |
Construction Phase |
CaTrans | Betcy Joseph | (510) 286-5097 | betcy.joseph@dot.ca.gov | |
Corridor System Management Plan |
CalTrans | Betcy Joseph | (510) 286-5097 | betcy.joseph@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$22,800 | $-7,800 | $15,000 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$2,220 | $101 | $2,321 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $25,020 | $-7,699 | $17,321 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$0 | $0 | $0 | $0 | |||
Design(PS&E) |
$1,405 | $101 | $1,506 | $2,900 | |||
Right of Way |
$815 | $0 | $815 | $289 | |||
Construction |
$22,800 | $-7,800 | $15,000 | $14,844 | |||
Total* | $25,020 | $-7,699 | $17,321 | $18,033 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
12/02/2001 08/30/2007 |
|
12/02/2001 08/30/2007 |
100 | 12/02/2001 08/31/2007 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/01/2007 08/31/2010 |
|
09/01/2007 08/31/2010 |
100 | 09/01/2007 08/19/2010 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
09/01/2007 05/13/2010 |
|
09/01/2007 05/13/2010 |
100 | 09/01/2007 05/25/2010 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
12/01/2010 12/31/2012 |
|
12/01/2010 12/31/2012 |
0 | 06/02/2011 07/17/2013 |
-6 -7 |
|
Begin Closeout Phase
End Closeout Phase |
01/01/2013 01/01/2014 |
|
01/01/2013 01/01/2014 |
75 | 12/31/2013 06/01/2016 |
-12 -29 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 09/01/2010 | 09/01/2010 | 100 | 09/01/2010 | 0 | ||
Implementation Date | 09/01/2010 | 09/01/2010 | 0 | 09/01/2010 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 965 | |
Lane Miles Added (HOV) | 1.8 | |
Lane Miles Added (Mixed) | 0 | |
Peak Period Time Savings (minutes) | 965.0 | 70432 |
Bond Funding Cost | |
---|---|
Adopted: |
$22,800,000 |
Current Approved: |
$15,000 |
Actual Expenditures: |
$14,844 |
Status as of December 31, 2023.